[Return to SCAPOSD Organizational Assessment, Chapters I-III] CHAPTER IV - EFFECTIVENESS OF ORGANIZATIONAL AND MANAGEMENT STRUCTURES Organizations generally go through similar life cycles. During the startup phase, the primary focus of management is staffing, particularly with technical personnel, and making strong initial progress in achieving the organization's mission. During this phase, "bugs" in key operational processes are worked out principally through trial and error. The establishment of formal organizational structures and management systems takes a back seat. So it has been with the District. However, given the District's growth and current levels of acquisition activity, effective organizational structures and management systems are overdue. The current lack of management systems is not only reducing the District's efficiency, but is a source of frustration for employees. Establishing such structures needs to be a focus in the coming year, as the investment will pay huge dividends. Consultants and the resources of other County departments should be utilized to assist with implementation wherever appropriate to ensure that the results are good and to allow District staff to continue carrying on their central mission. This is especially critical because current District staff is far more qualified in their technical specialties than they are in general management. In addition, it would be counter productive to take them away from their technical work more than necessary. Our recommendations for organizational structures and management systems are divided into the following key areas, and are intended to enhance operational efficiency and resource utilization, promote accountability, increase productivity, improve employee morale, encourage effective risk management, and enhance "customer service" and external relations:
Organizational Structure and Human Resources Management The current organizational structure is widely perceived as not effectively supporting the goals of the District. The basic organizational structure separates the professional staff into two groups -- 1) Planning and 2) Acquisitions. While this takes advantage of specialization, the two groups perceive each other as having very different orientations and priorities. Acquisitions staff see Planning as spending too much time perfecting background documents, penniRed and prohibited uses, etc., or trying to negotiate the "best" possible terms for land use; thus delaying their ability to effectively negotiate and close on projects. Conversely, Planning perceives Acquisitions staff as more concerned with "closing the deal," without enough consideration for the importance of project design. This conflict and the resulting lack of esprit de corps has begun to greatly impact morale. It may, in fact, be the greatest threat to the District's operations right now. This problem is compounded by lack of clear policies and direction from top management regarding the District's priorities, the roles and responsibilities of various staff members, and "standard operating procedures" for activities ranging from how to respond to inquiries to how best to balance the need to successfully close acquisitions versus the desire for a strong project design. Finally, the problem is exacerbated further by a lack of agreement among staff regarding interpretation of the District's mandate and no official policy to direct them. This has lead to different interpretations among staff, the most visible being disagreements with respect to trails policies. This has been a source of frustration and even conflict among staff. (This problem is addressed in greater detail elsewhere in the report.) While the above issues are clearly paramount, other areas can also be addressed. The District is not taking advantage of cross-training opportunities to increase organizational efficiency and effectiveness. There is a lack of training programs and established career paths. Finally, many staff members are underutilized. A critical source of these problems is that none of the current staff is managementoriented. There is tremendous talent on the technical, administrative, and "marketing" sides, but less so in management. The District is too small an organization to justify hiring a person solely to address management. Therefore, it is recommended that consultants and other County departments be relied upon as much as possible to effect change in these areas. The following recommendations are intended to address these areas. Rec IV.1 The District's General Manager must immediately establish a clear organizational structure, which delineates the roles of employees, and particularly, the reporting structure. Also, policies must be put in place for communicating with external shareholders, reaching key decisions on projects and other important matters, and maintaining quality control. Several actions will go a long way toward reducing internal conflicts and confusion about the roles of employees. The most serious manifestation of this confusion is the serious degree of conflict between Acquisitions and Planning staff. The current lack of understanding of reporting structures, distribution of work, and levels of authority is taking its toll on the organization. The first action for the General Manager is to verbally, and through written documentation and management decisions, define the major responsibilities and reporting relationships of the District staff. The following are specific conclusions and recommendations:
For the most part, these policies may be communicated verbally. Rec IV.2 Develop written policies to clearly define the direction and priorities of the District, and to provide procedural guidelines in key areas. Otherwise, employee conflict and frustration will persist. In particular, policy direction is needed in the following areas:
Rec IV.3 Improve communication for documentation of personnel policies and procedures. The General Manager needs to meet regularly with staff to discuss what is expected of them and to communicate the following:
The General Manager should take the lead in this effort. The District should be able to lean on the County for some of this -- such as developing job descriptions, and some of the policies listed above. It may be worth considering performance appraisal training for managers. It is a sensitive and difficult task. Rec IV.4 Strongly consider adopting a "proiect matrix" style of management to enhance utilization of staff, promote cross-training, promote efficiency and innovation in project management, and improve the working relationship between Acquisitions and Planning staff. Role flexibility should be encouraged, especially between Acquisitions Specialists and Planners. Under such a system, a Project Manager would be named for every project, as well as perhaps a two-person (or more) project team, to consist of at least one Acquisition and one Planning staff member. The Project Manager would be responsible for:
The project team would be responsible for research, project design -- virtually everything associated with the project. It should be the organization's goal to minimize the number of people involved in making decisions regarding the project, although this project management technique does not preclude the project team from calling on the services of other staff members. Under such a system, the Assistant General Manager would be responsible for the following:
The project matrix technique is designed to (a.) increase responsibility of professional staff; (b.) encourage project accountability; (c.) promote efficiency and innovation, and (d.) facilitate career development and cross training. This technique could improve employee morale and enthusiasm and reduce the day to day grind of the top management. It is strongly recommended that the General Manager and Assistant General Manager take on reduced Project Management activities to realize these objectives. Rec IV.5 Develop a plan for improving the utilization of Administrative staff. Although two administrative staff members, an Office Manager and Receptionist, were hired, their abilities are being underutilized. The Executive Assistant has been so busy over the last few months that there has been minimal time for training or transfer of knowledge and duties. However, it should be noted that a transition period is to be expected. In the meantime, the Office Manager brings valuable experience and capabilities. (For example, current operations have been hampered by the lack of staff resource management processes. The Executive Assistant is familiar with these processes, but these capabilities are not being utilized.) Similarly, there appear to be a number of administrative tasks which could be taken over by the Receptionist with minimal training. The Receptionist spent several years at a busy Federal office and would like to take on more responsibilities. The Receptionist could perform such activities as: sending out pre-action packages to new customers/owners, setting up appointments, organizing documents needed from the potential sellers, sending out an annual announcement to all easement owners and reminding them that they have an easement and that it will be inspected, sending out new owner packages upon closure of projects and maintaining hard copy project files. The following actions are recommended to improve utilization of Administrative staff:
The opportunities to improve the utilization of the Office Manager are particularly promising. Among the valuable activities in particular are 1) maintaining the project management/tracking system (as discussed below); and 2) working with the Executive Assistant to prepare more detailed budgets. The Offace Manager can also get involved in the acquisition process, such as maintaining boiler plates for p's & p's, appraiser RFP's, etc. The Office Manager should be provided with an off-the-shelf database package (e.g., MS Access or FoxPro) and begin development of a series of databases identified during an internal analysis of operations conducted by the District during the fall of 1997. Rec IV.6 Consider hiring additional staff after revised management systems are in place for at least six months and until other recommendations included in this report are implemented. In the meantime, consider reducing current project backlog by either: a) reducing the number of projects taken on for the next 12 to 18 months; or b) contracting with planners on a temporary basis. (The latter is preferable.) Rec IV.7 It is highly recommended that the next professional hired have real estate experience. Ideally, the new hire would have real estate and planning experience. This person would fill the roles of:
PROJECT MANAGEMENT SYSTEMS At present, there is no system in place for identifying 1) personnel on specific projects or 2) the particular phase of an ongoing project. This inhibits internal communications, reduces efficiencies, leads to management mistakes and increases response times to external and internal inquiries. Lack of project planning and budgeting is another source of ineffectiveness. The following is recommended: Rec IV.8 Formalize project management. Establish a comprehensive acquisition proiect tracking/management system, preferably automated. The amount of project activity and the dollars involved easily justify formalized project management systems.The following elements should be incorporated into such a Project Management System:
Rec IV.9 Establish performance standards, both for time and cost, for completing proiects, and reaching certain milestones. Time-to-completion estimates should be made for all projects being pursued or considered. Rec IV.10 Establish standard Project Close Out policies and procedures, including standardizing the contents required in the files of completed projects. Currently, key items may be missing in final project files. This may come to haunt the District whenever an outside party wishes to review the files, and could especially be a problem in cases where a transaction is being questioned. Incomplete files suggest a lack of professionalism and accountability to outside observers and would certainly give ammunition to those 'with an axe to grind" with the District. It could conceivably hurt the District efforts to thwart legal challenges. Rec IV.11 Develop and provide fairly detailed outlines or "road maps" to relevant stakeholders and external parties, especially landowners, which describe the acquisition process, including planning, necessary approvals, etc. ACCOUNTING AND COST TRACKING The benefits of effective cost accounting are many-fold and include the following:
Rec IV.12 Establish a simple automated cost accounting/tracking system to track the costs and labor hours incurred in performing the District's major activities. At present, there is no system in place to trace costs incurred by the District to perform its various activities. Because of this, there is a lack of reliable information on costs and resource utilization for budgeting purposes, for analyzing performance, and for making process adjustments to enhance efficiency. In addition, oversight agencies, such as the Board or the Authority, do not have the information they need to assess the District's operations. In fact, the Hood & Strong/MAI project team has found it difficult to assess staffing needs and operational performance for this study due to lack of data. It is typical for many governmental agencies to operate without such cost accounting systems in place, due to the nature of their operations. However, for many public agencies, such as water utilities and solid waste plants where operational efficiency is important, cost accounting is a critical management tool. The District needs to spend its limited resources as prudently as possible in order to maximize the "good" it does for the County in terms of its mandate. Furthermore, its operations are project-oriented. These characteristics strongly indicate a need for a cost tracking system. Both labor and other expenses should be tracked. Labor hours are easily tracked via biweekly and monthly time sheets that can be completed by employees in five minutes. Labor hours are converted to labor costs by establishing burdened hourly rates for each employee. Other costs would be tracked via travel and purchase vouchers, etc. The key to cost accounting is to separate out costs into the major activities in a manner that provides the most useful information to management. The first logical separation is between project related versus General & Administrative activities. However, further breakdown would be valuable. The ultimate goal is to track cost by major activity and relate these costs to specific acquisition (or other) projects. Several sub-activities may be grouped into a larger Activity Category. For a ten person operation, keeping the cost tracking system as simple as possible should be an important objective. The following exhibit provides and illustration of how to track costs (the illustration is not meant to be comprehensive).
Thus, an employee's time sheet would provide space for entering both an Activity Code (and sub-Activity Code) and a Project Code, if appropriate. A system would be established for tracking Accounts Payable transactions to specific activities and projects. Tracking can occur at the same time as vouchers are prepared for payment. The cost tracking/accounting system should be automated. However, the "system" should be placed into operation as soon as possible; that is, time sheets, accounts payable transacting, etc. should all begin supporting cost tracking even before automation is introduced. Implementation will require assistance from an outside consultant and other County department personnel, as identified, such as Internal Audits and ISD. The consultant is needed to establish the system, help select software, etc., while County personnel can provide ongoing support (to minimize fees to consultants). With proper training, the Cost Accounting System can be maintained by the District's administrative staff. PLANNING AND BUDGETING The planning and budgeting processes need to be more precise and formalized. Members of the Authority, Advisory Board, and Board of Supervisors have expressed that they do not have a clear view of the District's long-term, or even the current year's acquisition objectives, nor the Distfict's operational budget expenditures. There is no clear understanding as to whether the District needs a larger or a smaller budget. Also, due to a lack of precise planning, the District is spending an inordinate amount of time reacting to purchasing oppommities rather than proactively researching and pursuing highly desired acquisition targets. The District staff does not have a strong sense of the District's priorities. Rec IV.13 Update and revise the Acquisition Plan. Make it a more useful document for stakeholders by including greater detail of planned obiectives concerning purchases and other planned activities. The current Acquisition Plan reads a little too much like a mission and policy statement. It provides much less detailed information than it ought to. The District should work with its Board and Advisory Committee to develop a set of balanced, long-term acquisition goals, and to prioritize them into annual objectives. The effort should result in a more informative Acquisition Plan. The Plan should include formal three or five-year purchasing developed by the District. (The CIP should have greater detail that at present.) It probably should be produced annually, although each update does not necessarily require major changes in text (unless there are major changes in objectives). Such a Plan would assist the District staff in channeling their efforts appropriately and provide for a clearer stakeholder understanding of the District's objectives and activities. Rec IV.14 Develop strategic Annual Action Plan, based on the Acquisition Plan. In contrast to the Acquisition Plan, the Action Plan would primarily be for use by internal staff. It would be consistent with the Acquisition Plan, but would go further in clearly defining the year's purchasing and organizational objectives, as well as outline proactive strategies for acquiring desirable types of properties and meeting objectives. It would serve as a tactical plan to guide District staff in setting priorities, guide District managers in allocating resources, and provide specific strategies and performance goals for staff~ The document might include the following:
The Action Plan may be revised several times during the year in the event that goals are met sooner than expected or a particular strategy is clearly not working. Rec IV.15 Institute a process for developing annual budgets for Board approval, itemized in detail by the major activities, both for the District's overall operations and for anticipated land purchases. Generate simple quarterly variance reports showing actual expenditures versus budget. Coherent itemized budgets should replace the rules for establishing budgets based on a percentage of expenditures. INFORMATION SYSTEMS AND TECHNOLOGY Given the volume of records kept and documents generated by the District, the information system should be significantly upgraded. There is also a tremendous need for staff to be able to share data, since they often work on projects in teams. Rec IV.16 Establish a simple network and e-mail system to enable District staff to communicate and share data. This could be implemented by the County's Information Systems Office. A network would enable District staff to share project information and access boiler plate documents for developing presentations, RFPs, etc. It would be a fairly simple process to establish protocols regarding who can access what files. A computer workstation capable of handling a small network with GIS, graphics and desktop publishing production work would appear to suffice, given the District's overall workload. Such a system might be a 233-300 MHZ PC with a 4.2-6.4 MB hard drive, 128 MB RAM, and 4 to 8 MB Video RAM. Such a network would require a small amount of continued maintenance and administration, which may be available from the County's Information Systems Department. Rec IV.17 Augment automation of records to improve archiving of key information and to allow simple manipulation of data by management. FoxPro or Microsoft Access would likely be the best candidates for the database software. A problem for the District staff is that virtually all files are paper-based. Automation allows users to manipulate and cross-reference data in ways that can be very useful. In the event of staff turnover, paper-based files are inadequate for transferring organizational knowledge. The District already has a scanner to convert files into electronic data. The following are databases that should be established:
Rec IV.18 Establish a process for backing up electronic data. Store archival tapes or disks at an off-site location. Consider contracting with a document management/storage firm to protect sensitive and critical legal documents from accidental loss or destruction. The District has politically and legally sensitive documents that require security. The files on all closed District projects are kept on site. There are no off-site back-ups of the electronic files, nor are project paper documents stored in fire-proof or water-proof storage facilities. The District might also consider purchasing a ZIP-type external drive to allow the transfer and storage of large graphic images on 100MB disks. Rec IV.19 To the extent possible, standardize applications sof~ware used at the District, recognizing that some staff members may have specific preferences, hindering complete standardization. The Office Manager has been given Lotus 1-2-3 for a spreadsheet package, while the Planning Technicians use Microsoft Excel. Similarly, some staff members use MS WORD as their word-processing package, while others were given machines with only WordPerfect installed. There are constant communications problems caused by the lack of standardization and time is lost reformatting and converting files as they are passed back and forth between staff members. Even if some staff insist on using non-standard software, the final form of electronic data should be standardized to facilitate future retrieval and manipulation of data. Rec IV.20 Using a standardized software package, develop and implement a standardized set of acquisition documents, including planning documents and stewardship requirement documents and briefing packages for the various meetings for which the District prepares. |