COUNTY OF SONOMA
AGENDA ITEM SUMMARY REPORT

Department: Regional Parks
( X ) 4/5 Vote Required

Contact: Jim Angelo/Philip Sales -- Phone: 707-527-2041
Board Date: 10/26/99 -- Deadline for Board Action: 10/26/99

AGENDA SHORT TITLE:
Outdoor Recreation Plan and Appropriation Transfer

REQUESTED BOARD ACTION:

  1. Approval by the Board of Supervisors of the summary of the policy direction concerning the Draft Outdoor Recreation Plan from their meeting of September 14, 1999.

  2. Additional Policy direction requested.

  3. Approve an appropriation transfer of $15,100 from contingencies, $15,100 from Sonoma County Water Agency and $15,100 from Sonoma County Agricultural Preservation and Open Space District to Regional Parks operating budget for costs to complete additional work items.


CURRENT FISCAL YEAR FINANCIAL IMPACT

EXPENDITURES         ADD'L FUNDS REQUIRING BOARD      
Estimated Cost   $ 71,500   Contingencies
(Fund Name: )
  $ 15,100
Amount Budgeted   $ 20,000   Unanticipated Revenue
(Source: SCAPOSD & SCWA)
  $ 30,200
Other Avail Approp
(Explain below)
  $ 6,200   Other Transfer(s) $
(source: )
  $ _______
Additional Requested:   $ 45,300   Add'l Funds Requested:   $ 45,300

Explanation (if required): Carryover of encumbered consultant contract from FY 1998/99

Prior Board Action(s):

7/25/95 - Resolution by the Board authorizing agreement between SCAPOSD, SCWA and Regional Parks to fund the Outdoor Recreation Plan. 4/16/96 - Appointment of Citizens Advisory Committee. 8/24/99 - Board Workshop; 8/31/99 - Board Workshop; 9/14/99 - Board Workshop.

Alternatives - Results of Non-Approval:

1. Do not approve summary of policy direction - Return to Board for further direction. 2. Do not approve additional funding - The Plan will not be able to address the issues raised by the Board and the issues will remain unresolved

Background:

Request

  1. Approval by the Board of Supervisors of the summary of the policy direction concerning the Draft Outdoor Recreation Plan from their meeting of September 14, 1999.

  2. Additional Policy direction requested.

  3. Approve an appropriation transfer of $15,100 from contingencies, $15,100 from Sonoma County Water Agency and $15,100 from Sonoma County Agricultural Preservation and Open Space District to Regional Parks operating budget for costs to complete additional work items.

Discussion

Following the preparation of a Draft of the Outdoor Recreation Plan in May 1999, the Regional Parks Department sought policy direction from the Board of Supervisors on the Draft Outdoor Recreation Plan. Staff's recommendations were included in the Board report prepared for the meeting on August 24. The Board solicited public comment on the Draft Plan at meetings on August 24 and August 31.

On September 14, 1999, following the close of public comment, the Board provided policy direction to Regional Parks' staff. Based on the direction, the following summary of the Board's directions is organized according to the original policy questions presented to the Board on August 24, 1999.

A. Summary of Policy Direction Received by the Board

  1. Regarding the question of how the draft Outdoor Recreation P!an represent the purposes and goals envisioned by the Board of Supervisors, the direction given to staff was:

    1. To examine recreation opportunities on existing County and Water Agency property.

    2. To ensure that the Plan represents clear recommendations, highlighting those that are consistent with the 1989 General Plan and those that are not.

    3. To use the 20 acres per 1,000 population as stated in the 1989 General Plan in assessing regional recreational and open space park needs as the County's goal.

  2. Regarding the question of how the draft Outdoor Recreation Plan addresses the variety of outdoor recreation facilities that the Board envisioned, the direction given to staff was to strengthen the findings and recommendations contained in the Draft Outdoor Recreation Plan Supplemental Information in Chapter X on Community and Neighborhood Parks and Recreational Facilities for Organized Sports by:

    1. Adding additional opportunities for community and neighborhood parks in the unincorporated areas.

    2. Identifying opportunities in locations close to cities where the County could cooperate jointly with cities and other recreation agencies in providing park facilities including areas for organized sports.

    3. Strengthening policy language on partnerships with schools and cities on developing joint park/school sites in the unincorporated areas of the County.

  3. Regarding the question of how the draft Outdoor Recreation Plan adequately addresses the policy issues necessary to implement the Plan, the direction given to staff was to:

    1. Strengthen language that the County will only acquire property for parks and trails from willing sellers on lands in agricultural land use categories as designated in the 1989 General Plan.

    2. Prepare draft policy language to encourage partnering with cities to develop trail opportunities close to urban centers.

  4. Regarding the process, timeline and milestones for bringing the final draft of the Outdoor Recreation Plan to the Board, the direction given to staff was to:

    1. Agree with the timeline as presented but modify it to accommodate new items raised by the Board that may require further study or information.

    2. Agree to the holding of the six addition public meetings to solicit public input on Draft Plan following incorporation of policy direction from the Board.

    3. To identify the process for acquiring park properties, particularly those proper!ies that might be considered Opportunity purchases not called out in the General Plan.

    4. Develop an estimate of costs for the acquisition, development and operation and maintenance of park projects included in the 1989 General Plan and comparable costs for the additional park facilities proposed in the Draft Plan.

  5. Other Direction

    1. Add trail connector across Sonoma Mountain.

    2. Work with State Parks officials to expand the state parks in the County by at least 10,000 acres.

    3. Provide more analysis on public access opportunities to the Russian River.

B. Additional Policy Direction requested:

In addition both Supervisors Kelley and Reilly voiced concerns regarding specific outdoor recreation projects within their districts. Regional Parks staff is requesting Board policy direction on the following four issues:

  1. Supervisor Kelley was concerned about the proposal for a river access park in Alexander Valley.

  2. Supervisor Kelley and Supervisor Reilly expressed opinions about the inclusion of Kelly Road as a trail in the Draft Plan.

  3. Supervisor Reilly expressed a desire to have outstanding offers to dedicate additional Coastal access be accepted by public agencies.

  4. Supervisor Reilly requested additional public access to the Russian River in addition to the proposed Guerneville River Park. This includes Sunset Beach and year-round public access to Wohler Bridge.

C. Time Line/Cost Estimates

Based on the direction given by the Board, the following summarizes the estimated costs for revising the draft plan. This includes additional staff time to work with representatives of county and state agencies on specific issues, and using consultants to prepare additional information and data. This will include the preparation of data on likely acquisition costs, the preparation of a survey to determine likely voter attitudes to funding the implementation of the plan. The cost of this work is $71,500.

Existing funding of $26,200 is available and budgeted in Regional Parks budget for FY 1999/00.

  1. Consultant costs for facilitation and support for Citizen Advisory Committee and Public Meetings. $6,200 (already budgeted and encumbered with Consultant)

  2. The preparation of a draft environmental data for submission to PRMD. $20,000 (already budgeted)

    An additional $45,300 in funding is requested for the following items:

  3. Additional Extra Help staff time: The request for an additional $11,000 in extra help staff costs will enable the division to continue moving forward on the thirty-five funded capital projects while the plan is completed.

  4. Additional Consultant costs:

    1. The preparation of a revised programmatic level of likely acquisition costs. The background report to the Board indicated that this work could be accomplished for $6,000. This includes only the trail component of the Plan. A full program level for both parks and trails will cost $9,500.

    2. The preparation of a survey of likely voter attitudes to funding an expansion of the County park system. Staff and the consultant would work with the Board's subcommittee in developing the survey. $22,000.

    3. Additional consultant assistance in developing draft policy language to address issues raised by the Board will cost $2,800.

The time line for completing the above tasks is anticipated to take six months and a final Draft Plan presented to the Board in April 2000.

Regional Parks is requesting approval of an appropriation transfer of $15,100 from contingencies, $15,100 from Sonoma County Water Agency and $15,100 from Sonoma County Agricultural Preservation and Open Space District to Regional Parks operating budget for costs to complete additional work items. This is consistent with the previous funding for the Project.

Following the presentation of the final draft and prior to final adoption of the Outdoor Recreation Plan, an environmental review must be completed pursuant to the California Environmental Quality Act (CEQA). Based on consultations with Permit and Resource Management Department staff (PRMD), it appears that a program EIR is likely to be required. The EIR is estimated to cost between $75,000 and $200,000. Once the scope of the final plan has been determined the final cost of the EIR can be more accurately determined. The timeline on the EIR process has been estimated by PRMD to be 20 months.


ATTACHMENT (10/18/99)

OUTDOOR RECREATION PLAN TIMELINE

__________________  
1. Month 1: The CAC will meet to review the Board's direction resulting from the Workshop.
2. Months 2 - 4: Regional Parks staff will conduct six public workshops in each of the six sub-planning areas to present the Draft Plan and gather feedback.
3. Months 1 - 4: Staff from Regional Parks, County Counsel, County Administrators office and Permit and Resource Management Department will work to develop implementation detail recommendations such as streamlining the process of general plan and zoning amendments for properties acquired for outdoor recreation purposes.
4. Months 1 - 3: If approved, Regional Parks obtains current appraisal information for land acquisition costs at an estimated additional cost of $9,500.
5. Months 1 - 3: If approved Regional Parks obtains the services of a consultant to conduct a survey of likely voter attitudes on funding the implementation of the Outdoor Recreation Plan at an estimated additional cost of $22,000.
6. Months 4 - 5: Upon completion of the six public workshops, the CAC will consider any changes to the Draft Plan and make a final recommendation to the Board.
7. Month 6: The final draft Outdoor Recreation Plan will be presented to the Board.
8. Months 6-7: PRMD prepares the Initial Study for the Draft Plan. Program EIR likely, at least focused EIR. Coordination meetings with Parks over EIR issues and potential mitigations.
9. Months 8-10: PRMD coordinates with Parks on consultant selection process and initial EIR process, including ERC review and KFP process, issues NOP, Negotiates Contract Provisions, prepares Contract w/Counsel.
10. Month 10: NOP review period over; distribute comments.
11. Month 11: EIR Contract to Board for approval; initiate Draft EIR, Contract Administration, assist consultant with DEIR.
12. Month 14: Admin Draft EIR submitted; coordination with Parks/Counsel/District.
13. Month 16: Draft EIR Submitted; issue Notice of Completion, distribute DEIR for review.
14. Months 17-18 Draft EIR Review Period, including Planning Commission hearings on EIR and project and associated staff reports; distribute comments, initial consultant direction regarding preparation of responses.
15. Month 20: Final EIR completed; assist consultant with responses and FEIR mail out.
16. Months 21-22: Planning Commission Hearing(s) on Plan; two PC meetings; staff reports; research.
17. Months 24-25: Board Decision on Env Doc and Hearing(s) on Plan; two meetings, staff reports; prepare resolutions and findings.
18. Month 26: Adoption and follow-up; publications; NOD.

Resolution No. ____________
Sonoma County Administration
Building, Santa Rosa, Calif.
________________________

RESOLUTION OF THE BOARD OF SUPERVISORS, COUNTY OF SONOMA AUTHORIZING BUDGETARY ADRISTMENTS TO THE 1999-00 FINAL BUDGET FOR THE REGIONAL PARKS DEPARTMENT AND APPROPRIATIONS FOR CONTINGENCIES IN THE AMOUNT OF $45,300.00, REQUIRING FOUR-FIFTHS VOTE.

WHEREAS, the Board of Supervisors has adopted a Final Budget for the Regional Parks Department and Appropriations for Contingencies, and

WHEREAS, the Government Code allows for adjustments to the Final Budget during the 1999-00 Fiscal Year.

NOW, THEREFORE, BE IT RESOLVED, that the County Auditor-Controller is hereby authorized and directed to make the following budgetary adjustments:

  FINANCING USES:    
  COUNTY GEN FUND: REGIONAL PARKS   $11,000.00
203 032102-5110 Extra Help   34,300.00
203 032102-6500 Special Services   $45,300.00
       
  FINANCING SOURCES:    
  COUNTY GEN FUND: APPROP FOR CONTINGENCIES    
202 081018-9000 Appropriations for Contingencies   $15,100.00
  COUNTY GEN FUND: REGIONAL PARKS    
002 032102-2900 Contribution-SCAPOSD   15,100.00
002 032102-2943 Contribution-Water Agency   15.100.00
      $45,300.00

SUPERVISORS:

Kerns_______ Smith _______ Kelley_______ Reilly_______ Cale_______